St. Ann Municipal Corporation Office of the Contractor General November 2017

CHAIRMAN:

You did one for 400,000?

A:

I don't know if it is the 80,000. because what

generally happen, sir.

CHAIRMAN:

Go ahead.

A:

What happened sir, I might sign it for

$400,000.00, sir.

CHAIRMAN:

Yes.

A:

When it comes maybe one somebody get 80,

you may do one for 80, that one, is a bulk

signing, everybody don't go, I get my

80,000, I guh pay the people them wey I

work, sah.

80

Mr. Christie, during the mentioned hearing also indicated the sequence of events which took place subsequent

to his collection of the cheque in the amount of $400,000.00. Mr. Christie stated,

inter alia

, the following:

“CHAIRMAN:

And even though you signed the contract

for 400,000 you subcontracted out the

work?

A:

Yes, sir

.

CHAIRMAN:

And you subcontracted out the work to how

many persons, sir?

A:

That's what I couldn't tell you, sir. Mek I

guh back and tell you.

CHAIRMAN:

Let me ask you again.

A:

Yes, sir.

CHAIRMAN:

Of the 400,000 you say you got 170,000?

80

Transcript of Hearing involving, Mr. Reginald Christie, which was dated October 1, 2015 Pgs. 16-18.