St. Ann Municipal Corporation Office of the Contractor General November 2017
A:
It was draining and bushing so I have
two sections; some doing the draining
and some doing the bushing. So I have
about 10 drains, so one drain would
cost $8,000.00.
CHAIRMAN:
So how much was each person paid?
A:
The one that do the drain they were
paid; it was 10 drains, 5,000 each.
Who did the drain get $5,000.
CHAIRMAN:
And you said you had how
many people doing drains?
A:
About 10 doing drains.
CHAIRMAN:
So that's 10 times 5, 50?
A:
Yes, sir.
CHAIRMAN:
How the other 100,000 spend?
A:
It was for the bushing.
CHAIRMAN:
Yes, and how you spend the
other 100,000?
A:
I said for the drains.
CHAIRMAN:
Yes.
A:
Yes, sir.
CHAIRMAN:
You can't remember, sir?