St. Ann Municipal Corporation Office of the Contractor General November 2017

trustworthy persons within the Constituency

and I haven't had anything said otherwise

when their names are forwarded as

recommendations.”

170

Notwithstanding the foregoing, it is the OCG’s finding that of the nineteen (19) names listed on

letters dated December 17, 2013, December 18, 2013 and December 10, 2014,

171

which resulted in

the award of contracts by the St. Ann Municipal Corporation twelve (12) are associated and/or

affiliated with the People’s National Party. The extent of the affiliation and association are as

detailed in the table represented above.

Having regard to the responsibilities of the St. Ann Municipal Corporation for the implementation of

government contracts and in this regard, CDF funded projects, the OCG questioned whether the

Corporation had established mechanism which served as a verification process for the persons who are

recommended for the award of contracts within this specific threshold. The following responses were

provided by Mr. Alfred Graham, former Secretary Manager, St. Ann Municipal Corporation:

[OCG Officer]:

Do you have a due diligence process,

do you issue any instructions, or is

there anything written that would

indicate to the Works Department

that a vetting process or due diligence

process must be undertaken on the

names that are issued for payment of

a contract to be entered into?

A:

What would be the purpose of the due

diligence

,

because the Roads and

170

Transcript of Hearing involving Ms. Lisa Hanna, which was dated May 30, 2016. Pgs. 28-29

171

Refer to Appendices 3, 4, and 5.