_____________________________________________________________________________________________________
Page
312
of
554
St. Ann Municipal Corporation Office of the Contractor General November 2017
The process through which sub-contractors were selected for
the implementation of works in respect of contracts which
were awarded by the NSWMA in the amount of
$500,000.00.”
3.
I think the last time we met this was not submitted, so I
want to declare, I want to let you know that, all of these
money, once my name is on the cheque, it was handed over
to the Constituency Office... it was handed over to the
Constituency Office.
4.
What I would also want to say, in my delivery to the
Contractor General, if I have given any information that is
misleading or misguided to the Contractor General and the
Panel, I apologize, I sincerely apologize for that.
In
addition to that if there is any, which I don’t know of… if
there is any… cause I notice that the last time I came there
was a sheet, but it is really contracts, it relates to contracts,
it would have been the same information, the money would
have been handed over, if you should understand the money
would have been handed over to the Constituency Office
alright, you understand what I am saying?
5.
I handed over money to Miss Smith and Mr. Russell. I
collected money more than once yes, a few times I don’t
know exact. Here it is, one, two, three so I don’t know, I
don’t know.