St. Ann Municipal Corporation Office of the Contractor General November 2017
2016. The questions were directed to Ms. Smith on the basis that the contract was awarded under the
Capital Works –CDF Programme. The following representations were made in this regard:
“MR. DIRK HARRISON:
You don't know of Mr. Russell getting a
contract during the time that you were
working at the South East St. Ann
Constituency office?
MISS ANDREA SMITH:
While he was working there?
MR. DIRK HARRISON:
Yes, ma'am.
MISS ANDREA SMITH:
I don't remember, sir.
…
MR. DIRK HARRISON:
You have helped with the thing that they
call Capital Work CDF Programme, is that
something that falls within your portfolio,
ma'am? You deal with CDF?
MISS ANDREA SMITH:
I deal with CDF.
MR. DIRK HARRISON:
Since when, ma'am? Are you familiar
with South East Pedro Water Extension
Project, ma'am?
MISS ANDREA SMITH:
Yes, sir.
MR. DIRK HARRISON:
Does that fall within your portfolio?
MISS ANDREA SMITH:
Yes, sir.
MR. DIRK HARRISON:
And it fell within your portfolio?
MISS ANDREA SMITH:
The Pedro River Project?
MR. DIRK HARRISON:
Yes, ma'am.
MISS ANDREA SMITH:
I don't remember which year that was.
MR. DIRK HARRISON:
Look at this document madam, please.
(Witness shown document)
MR. DIRK HARRISON:
That is from the St. Ann Parish