St. Ann Municipal Corporation Office of the Contractor General November 2017
as such is not in a position to furnish the Office of The
Contractor General with requested information
.”
196
(OCG
Emphasis)
Colonel Pryce, in his response of September 25, 2015 to the OCG’s requisition dated September 22, 2015
indicated,
inter alia,
the following:
1.
“I had no knowledge of this allegation as I
became the Interim Executive Director on May 1,
2015. I became aware of this matter upon receipt
of your email dated September 22, 2015.
Upon receipt of the email, I enquired of my Executive
Assistant and the Parks Manager of the Parks
Department that is charged with the responsibility of
beautification and special projects implementation
resulting in the information that I am now
forwarding.
2.
The National Solid Waste Management Authority
is not aware of any contract or executed any works
at the ‘Prickly Pole Primary School
…”
197
(OCG
Emphasis)
196
Mr. Harrison’s September 24, 2015 response to the OCG’s requisition dated September 22, 2015.
197
Colonel Pryce’s September 25, 2015 response to the OCG’s requisition dated September 22, 2015.