Previous Page  52 / 601 Next Page
Information
Show Menu
Previous Page 52 / 601 Next Page
Page Background

__________________________________________________________________________________________

Page

52

of

554

St. Ann Municipal Corporation Office of the Contractor General November 2017

signed by the contractor on October 9, 2013; however, the stated contract commencement and completion

dates were October 7, 2013 and October 9, 2013, respectively.

Contracts Awarded to Lydia Morris

The OCG’s review revealed that a total of five (5) contracts were awarded by the St. Ann Municipal

Corporation with total payments amounting to $1,189,500.00. In relation to a contract which was in the

amount of $300,000.00, it is the OCG’s observation that both the commencement and completion date for

the contract preceded the date on which the contract was signed by the contractor. In this regard, the

contract was signed by the contractor on December 12, 2012, notwithstanding the fact that the contract

commencement and completion dates were stated to be December 4, 2012 and December 7, 2012. There

was, therefore, no formal contract in place during the contract execution phase.

In relation to the contract which was awarded in the sum of $489,900.00, the contract was signed by the

contractor on December 6, 2013; however the works commenced on December 5, 2013.

There were no rates and quantities applied on the contract document for the contract which was in the

amount of $20,000.00, it is therefore not clear as to the manner in which the estimates and/or contract value

were determined by the Corporation. Of the five (5) contracts awarded to Ms. Morris, two (2) were verified

as having been examined by the Internal Audit Department of the St. Ann Municipal Corporation.

Contract awarded to Mr. Oswald Jarrett

In relation to the contract which was awarded to Mr. Oswald Jarrett in the amount of $50,000.00, the OCG

found that the quantity of works performed, as well as the rates which were applied to the referenced works

were not stated on the contract document. It is therefore unclear as to the manner in which the St. Ann

Municipal Corporation determined the value of the works performed by Mr. Jarrett. Further, the OCG’s

review indicate that the date of the cheque which was made payable to Mr. Oswald Jarrett preceded the date

on which the contract was signed as well as the commencement and completion dates for the stated contract.

It is of interest to highlight that the mentioned contract and the payment made in respect of same were

examined by the Corporation’s Internal Audit Department.